This is an important final category of the first DUNG QUAT refinery, using R.O technology has not been implemented, so progress as well as requests for technical is very serious, to make sure the factory must operate all the workshops in August,2009
In March 2nd 2009, EPC contract will be signed between the Management Broad of the first DUNG QUAT refinery, using R.O technology with The Consortium of three companies : Drilling Mud Joint Stock Company, SEEN Technologies Corporation and VIET NGA Technologies Environment Company Ltd.the value of the contract is 44.7 billion VND, in which SEEN contractors play main role and organize all from the design, purchase goods to construction. |
|
|